not showing over allocated hours

J

jacobite

Hi - using 2003 to schedule studio time for the next year. In some instances,
I know a person has been over allocated, in the 'resource usage' sheet, no
tasks are showing as red. Any idea why?

cheers

j.
 
J

Jan De Messemaeker

Hi,
This is probably because there are no tasks in the resource Usage view, only
assignments.
It's the resoruc ethat is "res", not the assignment

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 