Not showing up as a task

D

drew

HI guys, I am pulling my hair out with this one.

I have setup a project plan in MS proj pro and assigned myself a
variety of tasks but when I go in to Project server I don't seem to
have anything assigned. I would also like to able to assign task in
Project server to resource but don;t seem able to do this either.

Any help would be very much appreciated.

Cheers
Drew
 
D

Dale Howard [MVP]

Drew --

Did you publish your tasks using either Collaborate - Publish - All
Information or Collaborate - Publish - New and Changed Assignments? If not,
you must do this step to make the tasks show up on team members' timesheets
in PWA. Also, you cannot assign resources to tasks in PWA; you must do this
in Microsoft Project. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top