K
Korwin
Hi there.
I've been checking out the Trial version of Project 2007, and I have a few
issues I cannot seem to make work.
The project that I plan on using Project for is 5 school districts that I
will be doing environmental consulting at over the next 2-3 years. Each
district has multiple buildings, with multiple tasks to be completed at each
building.
We have 4-5 weeks blocked out at each building, but with only 10 to 30 hrs
of actual work over that 4-5 week period (we need to wait for sample results,
etc, that spreads this whole thing out).
Is there any way that I can show that 4-5 week period blocked out for each
building but still be able to track the actual work completed? Everything I
try recalculates my end date or messes up another aspect. Any help?
Thanks.
--Kory
I've been checking out the Trial version of Project 2007, and I have a few
issues I cannot seem to make work.
The project that I plan on using Project for is 5 school districts that I
will be doing environmental consulting at over the next 2-3 years. Each
district has multiple buildings, with multiple tasks to be completed at each
building.
We have 4-5 weeks blocked out at each building, but with only 10 to 30 hrs
of actual work over that 4-5 week period (we need to wait for sample results,
etc, that spreads this whole thing out).
Is there any way that I can show that 4-5 week period blocked out for each
building but still be able to track the actual work completed? Everything I
try recalculates my end date or messes up another aspect. Any help?
Thanks.
--Kory