Notifications on the task updates

D

Darshini

Publish a project.
Change the project owner to somebody else other than you.
Task updates doesn't go to the new Project owner but keeps coming to the
publisher.

How to solve this?
 
D

Dale Howard [MVP]

Darshini --

The new owner of the project needs to open the project and do the following:

1. Click Collaborate - Publish - Republish Assignments
2. Select the "Become the manager for these assignments" option
3. Click OK

Doing so will cause Project Server to redirect task updates to the new
owner. Do know, however, that any pending task updates must still be
processed by the former project owner. Hope this helps.
 