T
tralbert
I am working on a project for my class in MS Project, and have the following
adjustments that have to be made.
1. At the end of schedule day 20, you are half complete with the tasks you
scheduled for Month I.
2. Actual Cost of Work Performed is 90% of the Budgeted Cost of Work
Scheduled (PV) for the tasks undertaken in Month I.
I know this means I'm behind schedule and over budget. In the tracking table
of the tracking Gantt chart I have indicated the % Comp. fields for all tasks
in Month I to be 50% complete.
I just do not know how to do part 2 of above. Changing the actual costs to
reflect them as being at 90% of the BCWS.
Any suggestions?
Thanks!
adjustments that have to be made.
1. At the end of schedule day 20, you are half complete with the tasks you
scheduled for Month I.
2. Actual Cost of Work Performed is 90% of the Budgeted Cost of Work
Scheduled (PV) for the tasks undertaken in Month I.
I know this means I'm behind schedule and over budget. In the tracking table
of the tracking Gantt chart I have indicated the % Comp. fields for all tasks
in Month I to be 50% complete.
I just do not know how to do part 2 of above. Changing the actual costs to
reflect them as being at 90% of the BCWS.
Any suggestions?
Thanks!