We modified one of the Enterprise Resource Outline Codes by renaming and
populating with our dept work teams. Does any one know what we need to do so
that when we are creating Views in Profolio Analyzer we can see this newly
defined code and its values? We have other resource outline codes showing up
which were completed as part of our initial EPS installation and we are not
sure how to do this now with new ones we need to add.
Any information to point us in direction of an answer is greatly appreciated.
thanks,
ljs
 
D

Dale Howard [MVP]

ljsexton --

The new outline code should show up after the OLAP cube rebuilds the next
time. Hope this helps.
 