david mcdermott
Having had no end of problems with Project Server most of
it now seems to be working properly. However I do not
seem to be able to create an OLAP cube. When I try to do
so I get the following message:
"The cube scheduled to be built on 14/07/03 at 15:21
failed.
(-2147221387) Cannot connect to the Analysis server on
computer 'willington'. Connection to the server is lost"
I have gone through lots of articles in technet and done
pretty much all the steps described in the
article 'Reporting in Microsoft Project Server: Microsoft
Project 2002' as this has a section entitled Setting Up
Portfolio Analyser Views in PWA'. The only section in
this that has not been done is 'Adding users to cube
database roles in SQL Server Analysis Services'. Is this
going to make the difference or is it likely to be
something else that is causing this problem?
Any help greatly appreciated.
Thanks
it now seems to be working properly. However I do not
seem to be able to create an OLAP cube. When I try to do
so I get the following message:
"The cube scheduled to be built on 14/07/03 at 15:21
failed.
(-2147221387) Cannot connect to the Analysis server on
computer 'willington'. Connection to the server is lost"
I have gone through lots of articles in technet and done
pretty much all the steps described in the
article 'Reporting in Microsoft Project Server: Microsoft
Project 2002' as this has a section entitled Setting Up
Portfolio Analyser Views in PWA'. The only section in
this that has not been done is 'Adding users to cube
database roles in SQL Server Analysis Services'. Is this
going to make the difference or is it likely to be
something else that is causing this problem?
Any help greatly appreciated.