I built a timesheet view in Analyzer and am comparing the results from this to a time card view I created under PWA's Resources/View Resource Assignments function. For a resource I have 9 hours on a project for a specific day but in the Analyzer timecard view I created it shows 13 hours for the resource on that same day. I verified that the total time for the resource on the project was 9 hours. I checked the project plan and found the entry to be 9 hours as well. I republished the task and then manually kickoff a build of the OLAP table. Still there is a difference.
Does anyone know why there would be a difference for it seems to me they should be exact? And how do I correct the OLAP table to reflect what the Project Plan and Resource timecard PWA view shows?