One Saturday a working day?

M

Marcus Pierce

I have a project plan on Project Server 2003 that needs to have one single
Saturday to be counted as a working day. I don't want to create a custom
enterprise calendar just for that one plan and I don't want to affect any
other plans. Any one know how we might accomplish this?

Thanks!

--Marcus
 
D

Dominic Moss

Marcus - you could "invest" your Enterprise with some additional "Task
Calendars" to model circumstances outside of normal operating hours, for
example a calendar that shows you working weekends only or even Saturdays
only as the situation you allude to may occur on more than one occasion.

You can then assign task calendars to individual tasks within a project
using the Advanced Tab of the Task Information dialogue box.

--
Dominic Moss

www.projectability.co.uk

Helping people achieve more with Microsoft Project

Tel +44 8707 303 400
Fax +44 8707 303 500
 