Only one of task's resources must report. How to do it?

S

szabti

Hi All,

I have a lot of tasks in my project with more then one resources. One of
these resources is a "leader" on that task. I want to send status report
request only to this "leader".

How can I do it?

(Project Server 2003, WSS)
 
M

Marc Soester

Hi szabti,

sorry this is not possible within Project Server. PS does not know the
difference between your task leader and another resource.
 