Jon Wilson
We have several users with task appearing in there timesheets that correspond
to task that were deleted from the project plan. Users can enter time to
these tasks that seem to go nowhere. Has anyone run into this before? Is
there something we can do (perhaps eliminating them from the database?)
to task that were deleted from the project plan. Users can enter time to
these tasks that seem to go nowhere. Has anyone run into this before? Is
there something we can do (perhaps eliminating them from the database?)