JodyJ

I created a task level custom outline code but it doesn't seem to be included
in my cube build. Was I wrong to expect it to show up? I was under the
impression that outline codes were included.
 
D

Dale Howard [MVP]

JodyJ --

The OLAP cube includes Project and Resource outline codes, but not Task
outline codes. If you wish to use Task outline codes, this requires
customization. Hope this helps.
 