B
bam
I had summary, sub tasks,, sub sub tasks, etc in my project schedule
Tasks were indented as I normally expect -- and I could collapse and expand
to see different levels.
For some reason -- not sure what I did -- but all tasks are now left
justified and it looks like there is no longer the indented hierarchy --
however, clicking on a summary task does display and hide sub tasks-- and
their outline levels are preserved (I displayed the outline level column).
It just looks like there is no indented structure. What happened?
Thanks
bmac
Tasks were indented as I normally expect -- and I could collapse and expand
to see different levels.
For some reason -- not sure what I did -- but all tasks are now left
justified and it looks like there is no longer the indented hierarchy --
however, clicking on a summary task does display and hide sub tasks-- and
their outline levels are preserved (I displayed the outline level column).
It just looks like there is no indented structure. What happened?
Thanks
bmac