When I click Import New Assignments I get "You don't have any assignments to
update." In Project Server I see the 2 tasks listed. The same problem
happens for my colleague. I did check the Server Configuration (Integration
with Spreadsheet). My Outlook test connection works and I adjust to import
tasks 8 months ahead.
Any ideas ? Thanks.
The project was set up as follows:
- Open MS Project and create Enterprise Account
- Open stand alone project file (Firearms Project Plan.mpp)
- Import Project to Enterprise
- Build Team from Enterprise
- Assign resources to each task
- Publish All Information to PS
update." In Project Server I see the 2 tasks listed. The same problem
happens for my colleague. I did check the Server Configuration (Integration
with Spreadsheet). My Outlook test connection works and I adjust to import
tasks 8 months ahead.
Any ideas ? Thanks.
The project was set up as follows:
- Open MS Project and create Enterprise Account
- Open stand alone project file (Firearms Project Plan.mpp)
- Import Project to Enterprise
- Build Team from Enterprise
- Assign resources to each task
- Publish All Information to PS