Outlook Integration causing errors in Outlook Calendar?

A

Anum_10

Appointments seem to be moving time slots on their own in outlook; or maybe
they are not.

Couple of our PMs are experiencing the following:

recurring meetings moved from the 3:00 pm to 5:00 pm slot on the calendar in
the daily view, but the item itself shows that it is scheduled for 3:00 pm in
the appointment view.

Any idea what is happening?

Could this be due to Project Server Outlook integration?

Please advise. Thanks!
 
Top