Outlook Timesheet Reporting

P

pajamasam

I'm a bit confused by the way Project (or Outlook) has calculated the
duration of tasks as seen in the Outlook Timesheet. The project is setup for
7 hr days. If a task's duration is 1 day, all is good....the Project Web
Access tab in Outlook will look something like this:
Actual work: 0 h
Remaining work: 7 h
Total work: 7 h

However, for a 2 day task, I'm seeing this in the Project Web Access tab:
Actual work: 0 h
Remaining work : 1.75 d
Total work: 1.75 d

Should I be seeing 2 d in the Remaining/Total work fields?

Please advice,
Smitty
 