Hi,
First of all thanks for reading this...
I create a new project plan & for some reason, I can't get some over
allocated resource to be leveled.
Most of the task types are ASAP, only 2 SNET & 1 MSO tasks.
At first I thought the problem may be due to linking the schedule w/
resource shared pool. So I saved the schedule file with another name then
under Tools > Resource Sharing> Share Resource option, I specified to "use
own resources" option.
Many of the tasks don't have true task dependencies, therefore, the
predecessor fields are blank, therefore, I set the priority numbers for the
logical flow.
What am I doing wrong? Please help!
Thanks a bunch!!!
Lilly
First of all thanks for reading this...
I create a new project plan & for some reason, I can't get some over
allocated resource to be leveled.
Most of the task types are ASAP, only 2 SNET & 1 MSO tasks.
At first I thought the problem may be due to linking the schedule w/
resource shared pool. So I saved the schedule file with another name then
under Tools > Resource Sharing> Share Resource option, I specified to "use
own resources" option.
Many of the tasks don't have true task dependencies, therefore, the
predecessor fields are blank, therefore, I set the priority numbers for the
logical flow.
What am I doing wrong? Please help!
Thanks a bunch!!!