B
Brian McCune
I have a resource who is set to work 8 hours per day. On some of the days in the resource usage view, she is only scheduled to work on a task for 2.5, but MS Project shows her as overallocated! Why is this?
At the top of the Resource Usage View, it shows actual and planned work - sometimes if I take the 2.5 hours out, and put it back in, the overallocation goes away. THIS DRIVES ME NUTS!
Am I inadvertently changing something when I remove and replace the identical hours on the identical task?
TIA!
Brian
At the top of the Resource Usage View, it shows actual and planned work - sometimes if I take the 2.5 hours out, and put it back in, the overallocation goes away. THIS DRIVES ME NUTS!
Am I inadvertently changing something when I remove and replace the identical hours on the identical task?
TIA!
Brian