I have a resource in two seperate plans - both tasks are under 8 hours in
total and the resource usage shows it in RED.
I understand for small tasks to change the start and finish times so they
don't overlap from the default of 08:00.
In this case though I have resource doing long tasks in two seperate projects.
I can see them at 7.6 hours in Red - but the tasks are months long - and you
cannot change the start time of one particular day during this task.
Any ideas how to rectify this?