P
Peter
I've been checking documentation and searching, but I can't figure out
this issue, probably because I don't know how to ask...
Say a person is working on a task in one project that is expected to be
finished in two weeks. During that time they will finish several small
tasks in other projects. How can I model this? If I schedule that
resource for both of these tasks they will be overallocated.
A very newbie question, I know, but I would greatly appreciate any tips,
including where in the documentation I should be reading.
Thanks in advance.
this issue, probably because I don't know how to ask...
Say a person is working on a task in one project that is expected to be
finished in two weeks. During that time they will finish several small
tasks in other projects. How can I model this? If I schedule that
resource for both of these tasks they will be overallocated.
A very newbie question, I know, but I would greatly appreciate any tips,
including where in the documentation I should be reading.
Thanks in advance.