Override resource calendars with project calendar

M

MP

PS2007

Is it possible to override resource calendars with project calendar?

Thanks you,
MP
 
D

Dale Howard [MVP]

MP --

In a Microsoft Project plan, the order of precedence for calendars is as
follows:

1. When you specify the Project Calendar (Project - Project Information)
for the project, this calendar governs the intial task schedule before you
assign resources to the task.
2. When you assign resources to a task, the resource calendars control the
task schedule.
3. You can override either the Project Calendar or the resource calendars
on a task by assigning a Task Calendar.

To assign a Task Calendar, double-click the name of the task and then click
the Advanced tab. Click the Calendar pick list and select the override
calendar, and then select the "Scheduling ignores resource calendars" option
as well. Click OK when finished. Hope this helps.
 
G

Gary L. Chefetz

MP:

The answer is no, but you can override the resource calendar with a task
calendar. Apply the Project standard calendar to the task as a task calender
and select to ignore resource calendars when scheduling.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top