Hi,
My manager wants to see the overtime cost we spent in all of our projects.
I didn't find a field in portfolio views designer. Am I missing something?
Can somebody please help how to get that info?

Thanks in advance
 
D

Dale Howard [MVP]

MNA --

Are you using Project Server 2003? If so, both the Overtime Work and Actual
Overtime Work fields are available as Totals at the top of the Pivot Table
Field List dialog when you create a new Portfolio Analyzer view. Hope this
helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
M

MNA

Thanks Dale!
does overtime work mean overtime cost ? I though it is number of hours.
What I am looking for is dollar amount. Any help please?

Regards,
Nadeem
 
D

Dale Howard [MVP]

MNA --

Oops! I am sorry, but I misread your original question. No, overtime work
and overtime cost are two different values. And you are correct in your
original statement that Overtime Cost and Actual Overtime Cost are not
available dimensions in the Portfolio Analyzer. Sorry if I have wasted any
of your time.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
Top