P
Pinocchio
What happens internally when I increase (or reduce) the field "Overtime" ?
I have a 50-hour task (duration 5days) assigned to a unique resources (125%)
I would like to set 10 hours as overtime to solve the over-allocation
warning.
Siuation 1:
Work: 50 hours
Overtime: 0
Unit: 125%
Timephased: 10 / 10 / 10 / 10 / 10
Situation 2: I set manually overtime to 10 hours
Work: 50 hours
Overtime: 10
Unit: 125%
Timephased: 12.5 / 12.5 / 12.5 / 12.5 / 0.0
Situation 3: I increase manually overtime to 11 hours
Work: 50 hours
Overtime: 11
Unit: 125%
Timephased: 12.82 / 12.82 / 12.82 / 11.53 / 0.0
Situation 4: I reduce manually overtime to 10 hours (similar to situation 2)
Work: 50 hours
Overtime: 10
Unit: 100%
Timephased: 10 / 10 / 10 / 10 / 10
Depending on my increasing or reducing the overtime allocation, MS Project
reacts differently.
Can anybody explain the logic behind this (still strange to me) behaviour?
Your MVB (Most Valuable Beginner)
Running Project 2002
I have a 50-hour task (duration 5days) assigned to a unique resources (125%)
I would like to set 10 hours as overtime to solve the over-allocation
warning.
Siuation 1:
Work: 50 hours
Overtime: 0
Unit: 125%
Timephased: 10 / 10 / 10 / 10 / 10
Situation 2: I set manually overtime to 10 hours
Work: 50 hours
Overtime: 10
Unit: 125%
Timephased: 12.5 / 12.5 / 12.5 / 12.5 / 0.0
Situation 3: I increase manually overtime to 11 hours
Work: 50 hours
Overtime: 11
Unit: 125%
Timephased: 12.82 / 12.82 / 12.82 / 11.53 / 0.0
Situation 4: I reduce manually overtime to 10 hours (similar to situation 2)
Work: 50 hours
Overtime: 10
Unit: 100%
Timephased: 10 / 10 / 10 / 10 / 10
Depending on my increasing or reducing the overtime allocation, MS Project
reacts differently.
Can anybody explain the logic behind this (still strange to me) behaviour?
Your MVB (Most Valuable Beginner)
Running Project 2002