S
soniva
Hi!
I have described my problem here
http://www.positivistene.org/2008/01/14/MSProjectAndResources.aspx
(sorry for the introduction on the case).
My main concern is that the developer's "non-productive-work" i
ignored in the project, and therefor the project when initiated i
already wrong. Programmers do not work 100% 37,5 hours a week, the
work closer to 75%.
But does this mean that an initial 10 hour assignment is going to b
completed in 12.5 hours, or will it take almost two full days calenda
time rather than a bit more than one.
I did a small test in project. In the resource view I created
developers working 65%, 50% and 100%. I then created an "implementatio
phase" and a "test phase" - I gave the developers 20 tasks to carry ou
- amount of work everything from 2h to 35h.
The result? Project uses my % input, but not for calculation in an
way. In theory (I believe) my 50% working developer _should_ spend 1.
weeks calendar time on set of tasks making out 37.5 hours (1 wor
week). But project ignores this fully and says that this well start o
monday and be complete following friday.
So my quesion is; how do I make sure that project uses the "max units
that I set and places a task over the actual available time, instead o
how it now works, basically just ignoring it fully
I have described my problem here
http://www.positivistene.org/2008/01/14/MSProjectAndResources.aspx
(sorry for the introduction on the case).
My main concern is that the developer's "non-productive-work" i
ignored in the project, and therefor the project when initiated i
already wrong. Programmers do not work 100% 37,5 hours a week, the
work closer to 75%.
But does this mean that an initial 10 hour assignment is going to b
completed in 12.5 hours, or will it take almost two full days calenda
time rather than a bit more than one.
I did a small test in project. In the resource view I created
developers working 65%, 50% and 100%. I then created an "implementatio
phase" and a "test phase" - I gave the developers 20 tasks to carry ou
- amount of work everything from 2h to 35h.
The result? Project uses my % input, but not for calculation in an
way. In theory (I believe) my 50% working developer _should_ spend 1.
weeks calendar time on set of tasks making out 37.5 hours (1 wor
week). But project ignores this fully and says that this well start o
monday and be complete following friday.
So my quesion is; how do I make sure that project uses the "max units
that I set and places a task over the actual available time, instead o
how it now works, basically just ignoring it fully