G
Gil
Hi all,
I want to use generic resources for modeling and checking how many
resources I will need for my project:
Let us say that I have my plan, and in the resource sheet I have
(among other resources) DEVELOPER, with 100% max units. After I assign
tasks to the developer and level him, I get the finish date of the
project.
Now, I want to check when will the project finish if I will have 2
developers. What is the best practice in this case? I thought to
change DEVELOPER max units to 200% in the resource sheet, but then
what? do I have to reassign all the tasks again and then level
resources again to get the new finish date? Is there a short way of
doing that?
After changing Max units to 200% I tried reassigning DEVELOPER to the
same tasks again but the assignment units was still 100%...
And lets say all the assignments are now 200%. Shouldnt Project now
AUTOMATICLY change start dates of tasks and therefore the start day of
the project should be earlier then before, or do I have to first
"level resources" in order for that to happen?
Thanks for helping me..
(using Project 2007)
I want to use generic resources for modeling and checking how many
resources I will need for my project:
Let us say that I have my plan, and in the resource sheet I have
(among other resources) DEVELOPER, with 100% max units. After I assign
tasks to the developer and level him, I get the finish date of the
project.
Now, I want to check when will the project finish if I will have 2
developers. What is the best practice in this case? I thought to
change DEVELOPER max units to 200% in the resource sheet, but then
what? do I have to reassign all the tasks again and then level
resources again to get the new finish date? Is there a short way of
doing that?
After changing Max units to 200% I tried reassigning DEVELOPER to the
same tasks again but the assignment units was still 100%...
And lets say all the assignments are now 200%. Shouldnt Project now
AUTOMATICLY change start dates of tasks and therefore the start day of
the project should be earlier then before, or do I have to first
"level resources" in order for that to happen?
Thanks for helping me..
(using Project 2007)