C
CQ
I am using the earned value field of VAC and EAC. What I want it to do is to
rollup (sum) the non-summary tasks for each section into the summary task.
Instead, it is calculating by some other means that I don't understand. I
have "actual costs are calculated by Microsoft..." unchecked. BAC is set.
However, EAC and VAC don't seem to rollup right.
Examples
This is the way it looks now:
BAC EAC VAC
SUMMARY TASK 2888 2722 166
Task One 963 907 55
Task Two 963 963 0
Task Three 962 963 0
This is what I expect:
BAC EAC VAC
SUMMARY TASK 2888 2833 55
Task One 963 907 55
Task Two 963 963 0
Task Three 962 963 0
What is happening here?
rollup (sum) the non-summary tasks for each section into the summary task.
Instead, it is calculating by some other means that I don't understand. I
have "actual costs are calculated by Microsoft..." unchecked. BAC is set.
However, EAC and VAC don't seem to rollup right.
Examples
This is the way it looks now:
BAC EAC VAC
SUMMARY TASK 2888 2722 166
Task One 963 907 55
Task Two 963 963 0
Task Three 962 963 0
This is what I expect:
BAC EAC VAC
SUMMARY TASK 2888 2833 55
Task One 963 907 55
Task Two 963 963 0
Task Three 962 963 0