J
Jpstewar
Scenario: Information from task A is needed for task B, which is a meeting
(or milestone) on the project plan - think of it as task 3, the MRC
pre-meeting. Task A does NOT have to be finished by the time of the meeting,
but some information is needed. We are calling A a predecessor to B, but
maybe that is not correct. We just need information from A so let's say A
needs to be 25% complete. Is there a way of capturing that?
(or milestone) on the project plan - think of it as task 3, the MRC
pre-meeting. Task A does NOT have to be finished by the time of the meeting,
but some information is needed. We are calling A a predecessor to B, but
maybe that is not correct. We just need information from A so let's say A
needs to be 25% complete. Is there a way of capturing that?