Is there a set of xml documentation for manipulating resource calendars using PDS in PS2003?
P PG Aug 25, 2005 #1 Is there a set of xml documentation for manipulating resource calendars using PDS in PS2003?
G Gary L. Chefetz [MVP] Aug 25, 2005 #2 PG: You can't manipulate calendars through the PDS. You must use the Project API to access these. Ask how to do this in the developer newsgroup at Microsoft.public.project.developer.
PG: You can't manipulate calendars through the PDS. You must use the Project API to access these. Ask how to do this in the developer newsgroup at Microsoft.public.project.developer.