R
rhcp
I am see an interesting situation where peak units is displaying very high,
1,000%+ and would like to know how the tool is calculating the number. I am
assumming that it would be work/duration for that given point in time on the
task but my manual calcultion does not match the display.
e.g. work entered is 8.55h for a standard 8h day I would expect to see 168%
but it is displaying a 98,100%. Total work for the task was 68.72h for a
9day period (each 8h). Work for the time period was entered as:
8.55h 7.27h 7.27h 7.27h 7.27h 7.27h 7.27h 6h 7.27h 3.27h
The work contour is set as Flat, using Project 2007 with Server 2007 where
resources are entering time trough My Task on PWA.
Any insight to how the peak is being calculated would be of great help.
Thank you,
rhcp
1,000%+ and would like to know how the tool is calculating the number. I am
assumming that it would be work/duration for that given point in time on the
task but my manual calcultion does not match the display.
e.g. work entered is 8.55h for a standard 8h day I would expect to see 168%
but it is displaying a 98,100%. Total work for the task was 68.72h for a
9day period (each 8h). Work for the time period was entered as:
8.55h 7.27h 7.27h 7.27h 7.27h 7.27h 7.27h 6h 7.27h 3.27h
The work contour is set as Flat, using Project 2007 with Server 2007 where
resources are entering time trough My Task on PWA.
Any insight to how the peak is being calculated would be of great help.
Thank you,
rhcp