J
john
When I update a project plan as the project manager I would expect that if I
mark a task complete that it would either drop off the assigned resources
time sheet or at least show complete on the time sheet. Am I missing
something or is this expected functionality?
Here's a more detailed explanation. I assign resource "bob" to task "create
form" with a duration of 8 hours. I find out that bob has already done the
task so I update the "create form" task on the project plan to 100% complete.
I save and publish all changes but the task still shows up on bob's
timesheet as 8 hours 0 percent complete.
Any help would be much appreciated.
mark a task complete that it would either drop off the assigned resources
time sheet or at least show complete on the time sheet. Am I missing
something or is this expected functionality?
Here's a more detailed explanation. I assign resource "bob" to task "create
form" with a duration of 8 hours. I find out that bob has already done the
task so I update the "create form" task on the project plan to 100% complete.
I save and publish all changes but the task still shows up on bob's
timesheet as 8 hours 0 percent complete.
Any help would be much appreciated.