M
Michelle
I have a project manager whom after receiving updates from
PWA wants to put the remaining work for a task to zero.
The problem that is occuring is that after he zero's out
this remaining work the percent complete is not changing
to 100%. Does anyone have any ideas as to why this is
doing this? Is he missing a step that will automatically
mark this task as 100%?
Also as part of the team's weekly status meeting they
review the updates to the plan and then assign any new
tasks that have been added to a certain week. After the
task assignments are completed the project manager saves
the plan and publishes. The team then reviews all
assignments for the next week in the resource assignment
view in PWA. The problem is that after the PM publishes
the assignments the resources and the project manager then
only see a portion of the assignments in the resource
assignment view in PWA. Any idea why this is doing this?
Thanks!
Michelle
PWA wants to put the remaining work for a task to zero.
The problem that is occuring is that after he zero's out
this remaining work the percent complete is not changing
to 100%. Does anyone have any ideas as to why this is
doing this? Is he missing a step that will automatically
mark this task as 100%?
Also as part of the team's weekly status meeting they
review the updates to the plan and then assign any new
tasks that have been added to a certain week. After the
task assignments are completed the project manager saves
the plan and publishes. The team then reviews all
assignments for the next week in the resource assignment
view in PWA. The problem is that after the PM publishes
the assignments the resources and the project manager then
only see a portion of the assignments in the resource
assignment view in PWA. Any idea why this is doing this?
Thanks!
Michelle