Susan --
The other thing you might look for is resources assigned to summary tasks.
Apply the Gantt Chart view with the Entry table applied, and then drag the
vertical split bar all the way to the right. Examine the Resource Names
column to determine if you have resources assigned to any summary tasks. If
you do, remove them, as resources should never be assigned to summary tasks.
Let me know if this helps.
Susan said:
Dale, I did as you suggested and I was able to get rid of anything set to
0%. However I still have summary tasks that show 98% and 99% complete, but
all of the sub-tasks are 100%. Could it be tasks that were deleted from the
project? Thanks for your help.100%, when you filter to show only incomplete tasks nothing shows up, (which
is right). However when you view the statistics under project information it
shows 99% complete. Am I missing something obvious that needs to be updated?