Perform Work on Weekend but Not Start on Weekend

M

Marv

Although Saturday/Sunday are workdays, a task does not begin on a weekend.
Can I set some sort of constrant that allows work to be performed on a
particular day of week but not started on that date? Thank you.
 
R

Rod Gill

The only way you are going to achieve that is by manually applying a 7 day
calendar to Tasks that won't finish by Friday close of business. Any other
method will allow tasks to start on the weekend as well.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Marv said:
Although Saturday/Sunday are workdays, a task does not begin on a weekend.
Can I set some sort of constrant that allows work to be performed on a
particular day of week but not started on that date? Thank you.

__________ Information from ESET Smart Security, version of virus
signature database 4878 (20100218) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4878 (20100218) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
M

Mike Glen

Hi Marv,

There's no automatic way and manual adjustments can be aided, but I think you need to consider what the majority of tasks require and then schedule those. For example, are most tasks worked on over the weekend or is it just a few? Must any of the tasks not start at the weekend or only a few? If you can narrow down the minority, it might be worthwhile manual adjustment. A certain amount of automatic adjustment can be achieved by creating a milestone between tasks and setting that milestone (via a calendar) to occur 1 minute before start work on Monday.


FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



Although Saturday/Sunday are workdays, a task does not begin on a weekend.
Can I set some sort of constrant that allows work to be performed on a
particular day of week but not started on that date? Thank you.
 