P
Parag Lawate
Hi All,
Anybody expert on MS projects ?
I need help on Microsoft projects, following is my question -
do MSP have place to store periodic quantities and apply respective rate to
come-up with value per task
foll is example
In MSP
hrs
rate
Amt
Jan
10
5
50
Feb
20
6
120
Mar
30
7
210
total
60
380
as i understand MSP can store the rates ,but can it also store multiple
quantities per task?
Can anyone guide to 'forums' where this question can be raised?
Thanks,
Parag
Anybody expert on MS projects ?
I need help on Microsoft projects, following is my question -
do MSP have place to store periodic quantities and apply respective rate to
come-up with value per task
foll is example
In MSP
hrs
rate
Amt
Jan
10
5
50
Feb
20
6
120
Mar
30
7
210
total
60
380
as i understand MSP can store the rates ,but can it also store multiple
quantities per task?
Can anyone guide to 'forums' where this question can be raised?
Thanks,
Parag