T
T
I am very new to Microsoft Project Server. I have been able to setup a
Server and Upload a Microsoft Project file to the pwa site.
Some of the tasks in the file have resources allocated to them and others do
not. What I would like to do is make it so my manager can download all tasks
and meetings that are not 100% complete regardless of the resources allocated
to them. Any help would be appreciate because right now when I do everything
using my Administrator account (all on one PC) to test, I am only able to
download 3 of the 50 some incomplete tasks.
Thanks
Server and Upload a Microsoft Project file to the pwa site.
Some of the tasks in the file have resources allocated to them and others do
not. What I would like to do is make it so my manager can download all tasks
and meetings that are not 100% complete regardless of the resources allocated
to them. Any help would be appreciate because right now when I do everything
using my Administrator account (all on one PC) to test, I am only able to
download 3 of the 50 some incomplete tasks.
Thanks