J
Joel Martin
The instructions for using the optimistic, pessimistic, and expected fields
say simply "On the View menu, point to Toolbars, and then click PERT
Analysis." However, I only am able to see this option sometimes, and I have
no idea what the variable is. It was available when I first started working
with Project, then when I wanted to use it, I couldn't find it, finally gave
up, and then it was there again when next I opened Project. Now it's not
there again. Is there some enterprise setting that someone else is changing
(I'm using Professional, and there's a Project Server, although only a few
other people have access at this point)?
say simply "On the View menu, point to Toolbars, and then click PERT
Analysis." However, I only am able to see this option sometimes, and I have
no idea what the variable is. It was available when I first started working
with Project, then when I wanted to use it, I couldn't find it, finally gave
up, and then it was there again when next I opened Project. Now it's not
there again. Is there some enterprise setting that someone else is changing
(I'm using Professional, and there's a Project Server, although only a few
other people have access at this point)?