phases duration shows in decimal .

S

Sam

in project plan of project professional many phases showing duration in
decimal like 2.23

but we didnt use any task with duration like that in decimal.
and all tasks duration values in whole amount .

why phases duration showing in decimal .

kindly reply me soon.
 
M

Mike Glen

Hi Sam,

Welcome to this Microsoft Project newsgroup :)

Two possibilities. I guess you mean summaries of phases. A summary's Duration is measured from the Start of its first task to the Finish of its last task, and thus could well span part of a day because of resources availability etc.

Or it could be caused by a miss-match of Calendars and working time. See FAQ Item: 5. Default Working Hours

Finally, if you're using Project Pro and Server, then try posting on the microsoft.public.project.server newsgroup (forum). Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm


Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
in project plan of project professional many phases showing duration in
decimal like 2.23

but we didnt use any task with duration like that in decimal.
and all tasks duration values in whole amount .

why phases duration showing in decimal .

kindly reply me soon.
 
Top