Physical % complete on Gantt chart?

K

Kamil Dursun

Hi,

I would like to show the physical % complete instead of % complete on the
Gantt chart (PJ 2003 Pro).

I changed the definition of the progress row in the G.C. view from "Complete
through" into "Physical % Complete" but have problems.

First, when I drag the %, it immediately jumps into 100%. If I adjust the
Physical % complete field in the Tracking table, it follows but sometimes
vanishes completely. Furthermore, for split tasks the bar shows also in the
period where there should be no work. Altogether it behaves very strangely.

Is there anybody who has experience with using this field?

Thanks
Kamil
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top