R
Rob
Hi,
Project 2007 pro - No server yet though.
After much effort to do calculated fields to measure expected/planned %
complete to actual % complete I have realized how lame the idea is overall,
and my results have been less than par with summary tasks never working out
just right. I want to move into EVM reporting with a Gantt chart and S Curve.
My project has had three reporting cycles already. I crafted these nifty
TPS reports (Time Project Sheet - I like humor) for tracking task start, work
complete during cycle(1 week), est. remain work, and task finish that
everyone completes once a week for all of their tasks.
Here are the steps I think I need.
1. Enter costs for everyone. - I am going to use the $1 earned
schedule/effort idea.
2. Delete all progress. - Is there a known copy/paste method for removing
and adding work over time?
3. New Baseline.
4. Re-Apply progress. - Again... shortcut to this?
Let me know if these steps get me to where I can do the Gantt chart and S
Curve as if I had been doing EVM all along.
Thank you for all of your help ahead of time.
Project 2007 pro - No server yet though.
After much effort to do calculated fields to measure expected/planned %
complete to actual % complete I have realized how lame the idea is overall,
and my results have been less than par with summary tasks never working out
just right. I want to move into EVM reporting with a Gantt chart and S Curve.
My project has had three reporting cycles already. I crafted these nifty
TPS reports (Time Project Sheet - I like humor) for tracking task start, work
complete during cycle(1 week), est. remain work, and task finish that
everyone completes once a week for all of their tasks.
Here are the steps I think I need.
1. Enter costs for everyone. - I am going to use the $1 earned
schedule/effort idea.
2. Delete all progress. - Is there a known copy/paste method for removing
and adding work over time?
3. New Baseline.
4. Re-Apply progress. - Again... shortcut to this?
Let me know if these steps get me to where I can do the Gantt chart and S
Curve as if I had been doing EVM all along.
Thank you for all of your help ahead of time.