the task is to build a wall and is scheduled to take 8 hours.
4 hours is needed to go to the store and buy bricks and dig the foundations.
This is 50% complete (in terms of time) but as you have not layed a brick
it's physically less complete.
The remaining 4 hours are used to lay the bricks where the majority of the
physically complete % value is earned.