Physical % Complete

R

Robin Roe

Hi

We need a way of letting the Project Manager enter what physical % of a Task
is complete (aswell as the % of work complete). I have looked at using the
'Physical % Complete' field, but this unfortunately does not roll up which
isn't very good as I would also like the Directors to get an overview of
Physical % complete on all projects.

Any ideas would be most appreciated

Thanks
 
G

Gérard Ducouret

Hello Robin,

The Physical % Complete will never rollup. It is just used to alter the
calculation of BCWP in the Earned Value table.
But you can customize a Number(x) field with a simple formula which picks up
the Physical % Complete. For this customized field, you can check the option
:
Rollup : Sum

Gérard Ducouret
 