R
ritpg
I believe I have followed all the MS instructions for making this
happen. But there are 2 summary tasks that show a value of 0% for
Physical % Complete. All other summary tasks (including the 1st level
summary task) show a composite Physical % Complete. In the MS
instructions, 3 criteria are listed for "forcing" Project to roll
Physical % Complete up to summary tasks:
1) Earned value calculation is set to Physical % Complete (which I
believe I have done)
2) Resource assignments on tasks have a Standard Rate (which I believe
is true)
3) The baseline value used for Earned Value Calculation is populated
I was not sure about #3 so I saved a new baseline (with a new name).
I have run into this problem before when someone added a new task and
did not set the Earned Value Method to Physical % Complete for the new
task. As soon as I set the Earned Value Method to Physical % Complete
for the new task, the rollup to the summary task occurred.
Additional background: the 2 summary tasks that are not showing the
rollup are 2 that I created after the baseline had been saved when I
needed to regroup some primitive tasks. As I imply above, the Earned
Value Method is set to Physical % Complete for every task in the
schedule. But I cannot tell you the order in which that was done.
Thanks so much for any an all inputs.
happen. But there are 2 summary tasks that show a value of 0% for
Physical % Complete. All other summary tasks (including the 1st level
summary task) show a composite Physical % Complete. In the MS
instructions, 3 criteria are listed for "forcing" Project to roll
Physical % Complete up to summary tasks:
1) Earned value calculation is set to Physical % Complete (which I
believe I have done)
2) Resource assignments on tasks have a Standard Rate (which I believe
is true)
3) The baseline value used for Earned Value Calculation is populated
I was not sure about #3 so I saved a new baseline (with a new name).
I have run into this problem before when someone added a new task and
did not set the Earned Value Method to Physical % Complete for the new
task. As soon as I set the Earned Value Method to Physical % Complete
for the new task, the rollup to the summary task occurred.
Additional background: the 2 summary tasks that are not showing the
rollup are 2 that I created after the baseline had been saved when I
needed to regroup some primitive tasks. As I imply above, the Earned
Value Method is set to Physical % Complete for every task in the
schedule. But I cannot tell you the order in which that was done.
Thanks so much for any an all inputs.