% physical Work field in project server?

  • Thread starter Porfirio Fuentes Martínez
  • Start date
P

Porfirio Fuentes Martínez

In Project 2002 Professional there is a field named % Physical Work, its
used to calculate BCWP using an arbitrary percentage of advance, instead of
% of Work.


I can't find this field when I try to define a new view in Project Server
2002.

Is there any way to add it to project server? If not, is there a way to
generate earned value reports replacing the fields used for calculations,
but preserving the formulas?

Thanks

Porfirio Fuentes
 
P

Porfirio Fuentes Martínez

Correction, the fields names I'm talking about are wrong, the correct ones
are:

where I refer to % of Physical Work it should be: Physical % complete
where I refer to % Work it shold be: % Complete

I get confused because I was working with a spanish version. :)

Thanks

Porfirio
 