Pick Lists in Project 2002 Web Access

C

cnewlon

We are having problems with several of the drop down lists
in MS Project 2002 Web Access.

When we want to delegate a task, the drop down list of
people to which the task can be delegated fails to respect
the RBS structure. It is possible for someone with
delegation authority to delegate tasks to anyone in the
entire enterprise.

Conversely, when we try to send nonworking time to our
project manager, the window that should have a pick list
of all the project managers is completely empty.

Does anyone know where these things are set or controlled?
 