J
jb
Hi,
I have some "beginners" questions on planning and tracking, which I
would appreciate some advice on. My project has roughly a dozen team
members and takes nine months to complete.
Following Mike's excellent tutorials, I have entered my tasks and did
the dependency logic. I assigned the resources (sticking to the rule of
one resource per task), used leveling and noticed that the project
takes unexpectedly long.
So I thought, well some of the resources have very similar skills, why
not pool them? And instead of assigning DeveloperA to one task and
DeveloperB to another, I replaced every reference with "Developer" and
increased the availability of "Developer" to 200%. I did that with only
non-key resources.
Leveling yielded a better result. Good. Assuming that the team has the
flexibility, would I run into any surprises using this technique to
determine the end date? Is this a common technique or is my reasoning
flawed?
Now that I have two Developers with similar skills how can I track the
costs if the two have different rates (A is higher than B)? Remember
that I can no longer see in the plan if A or B is working on a task.
The last question also relates to tracking: assume that during the
course of the project I have to change the resource assignment of some
task. C is now supporting D on a task. Do I simply add C to a task
(with the above quoted rule: one resource per task, I would probably
add a task for C in that work stream)? Would project get confused in
terms of tracking (progress, time, duration, EV, etc.) compared to the
baseline?
Thanks in advance,
Stefan
I have some "beginners" questions on planning and tracking, which I
would appreciate some advice on. My project has roughly a dozen team
members and takes nine months to complete.
Following Mike's excellent tutorials, I have entered my tasks and did
the dependency logic. I assigned the resources (sticking to the rule of
one resource per task), used leveling and noticed that the project
takes unexpectedly long.
So I thought, well some of the resources have very similar skills, why
not pool them? And instead of assigning DeveloperA to one task and
DeveloperB to another, I replaced every reference with "Developer" and
increased the availability of "Developer" to 200%. I did that with only
non-key resources.
Leveling yielded a better result. Good. Assuming that the team has the
flexibility, would I run into any surprises using this technique to
determine the end date? Is this a common technique or is my reasoning
flawed?
Now that I have two Developers with similar skills how can I track the
costs if the two have different rates (A is higher than B)? Remember
that I can no longer see in the plan if A or B is working on a task.
The last question also relates to tracking: assume that during the
course of the project I have to change the resource assignment of some
task. C is now supporting D on a task. Do I simply add C to a task
(with the above quoted rule: one resource per task, I would probably
add a task for C in that work stream)? Would project get confused in
terms of tracking (progress, time, duration, EV, etc.) compared to the
baseline?
Thanks in advance,
Stefan