M
metimmee
What is the best way to incorporate vacation time within a project? I
have 5 members of a team that are allowed to take their vacation at
any time during the project, providing the manning doesnt drop below 2
personnel. Initially I added a contingency period to the end of the
project which took into account unallocated vacation. If a slip for a
project phase occured due to absence, I would take that time from the
contingency period, keeping delivery at a constant date.
Management arent happy with this solution. Any advice on how I should
incorporate vacation time?
Thanks.
have 5 members of a team that are allowed to take their vacation at
any time during the project, providing the manning doesnt drop below 2
personnel. Initially I added a contingency period to the end of the
project which took into account unallocated vacation. If a slip for a
project phase occured due to absence, I would take that time from the
contingency period, keeping delivery at a constant date.
Management arent happy with this solution. Any advice on how I should
incorporate vacation time?
Thanks.