T
The_WI_Cheezer
How can this be possible for the summary of Remaining Work? The total should
be 13 hours not 193? There are no other indented tasks.
Summary Task: Project Close-out 193 hrs
Assess customer satisfaction 2 hrs
Review planning template / adjust based on lessons learned 2 hrs
Review and recognize team performance 2 hrs
"Archive the project records (MS Project server, Prosite, other)" 3 hrs
Draft and submit Project Closing Report to Project Executive 4 hrs
be 13 hours not 193? There are no other indented tasks.
Summary Task: Project Close-out 193 hrs
Assess customer satisfaction 2 hrs
Review planning template / adjust based on lessons learned 2 hrs
Review and recognize team performance 2 hrs
"Archive the project records (MS Project server, Prosite, other)" 3 hrs
Draft and submit Project Closing Report to Project Executive 4 hrs