PMGuy --
Project Server 2003 does not allow you to have two PM's who manage every
task in the project, but it DOES allow each PM to manage different sets of
tasks in the project. For example, PM#1 might need to manage Phase I and
Phase II, while PM#2 must manage Phase III through Phase V. To support this
scenario, your project Server administrator would need to change the default
permissions in Project Server and allow every PM to be able to open and edit
every project in the system. To accomplish this, he/she would need to do
the following:
1. Log into PWA with administrator permissions.
2. Click Admin - Manage Security.
3. Select the My Projects category and click the Modify Category button.
4. In the Projects section, select the "All current and future projects..."
option
5. Click the Save Changes button.
After your Project Server administrator does this, each of the PM's who each
need to manage a section of the project will need to do the following:
1. Open the project and selects the tasks that he/she will manage.
2. Click Collaborate - Publish - Republish Assignments, selects the
"Selected Items" choice from the pick list at the top of the dialog, selects
the "Become the manager for these assignments" option, and clicks the OK
button.
3. Save and close the project.
After each PM completes the above set of three steps, Project Server 2003
will route task updates to the correct PM for each section of the project.
Hope this helps.