Portfolio Analyser

O

Oliver

Is there any possibility to insert calculated fields like "baseline work 10"
in the portfolio analyser?

Thanks for your help
 
R

Rick Roszko

The OLAP cube only processes resource (e.g. Resource Sheet) based
information, not task (e.g. Gantt Chart) based information. Only Enterprise
Resource Outline Codes can be used in the OLAP cube (out-of-the-box).
 
O

Oliver

Hi Rick,

maybe I´m wrong but I think its a little bit different. The OLAP cube also
creats summaries eg for work. I´ve there the baseline work (summary) for a
project. What I additional need is eg the baseline work 10 for a project

Oliver
 