RG said:
In PWA, go to Admin >> Manage Views >> Select Portfolio Analyzer >>
Modify View >> Type the correct Cube name >> Apply I hope this helps
RG's instructions are for Project Server 2003. For Project Server
2002, you will need to download a utility to modify the cube that a
view points to.
http://www.epkgroup.com/download.htm
A Portfolio Analyzer view is assigned to a single cube. However, you
could build multiple cubes and have some Portfolio Analyzer views point
to one cube and other views point to other cubes. One scenario where
this might be feasible is if you want to have a monthly cube build that
encompasses a longer range view of project and resource information.
David